Plan Revisions Hang Up Montezuma County Courthouse Construction

Austin Cope
/
KSJD

Montezuma County officials are growing concerned about a delay in starting foundation work for the new combined courthouse project in Cortez.

Owner’s rep Monty Guiles told the county commissioners Monday that the city has not yet issued a permit for the excavation because the county’s revised site plan was only  being submitted by architects this week. Guiles said workers need to start on the foundation as soon as possible because doing concrete work in cold weather is more expensive. Guiles said he believes city staff are trying to get the approval expedited, but there has been “a little culpability” on all sides.

Gail Binkly is a career journalist who has worked for the Colorado Springs Gazette and Cortez Journal, and was the editor of the Four Corners Free Press, based in Cortez.